CLIENT:
OIL PIPELINES OPERATION ENTERPRISE "FRIENDSHIP" SA
(PERN "PRZYJAŹŃ" SA)
SCOPE OF WORKS:
SP ST-1 Adamowo
Modernization of the pump unit.
(2004)
Jarotki
Revamp of the 1st pipeline DN 500 in marsh area and passages under roads.
(12.2003 - 08.2004)
ST-3 Góry
Modernization of gate-valves and non-return valves chambers.
(2003)
BS Plebanka
Modernization of the process pipelines and bypasses with shutoff valves on the “Friendship” pipeline.
(2002)
Installation of the filters on pump unit pipelines.
(2002)
Mielinek near Włocławek
Revamp of the 1st pipeline DN 500 in marsh area and passages under roads in especially unfavourable water-soil conditions during autumn-winter period.
(2002)
SP ST-6 Łupowo
Construction of Discharge Room and Pump Station No 6.
(2002)
|