CLIENT:
PKN ORLEN SA (OSTRÓW WIELKOPOLSKI)
TANKS Z-11,
Z-12 i Z-13
Supply and erection of the double-shell storage tanks no Z-11,
Z-12 & Z-13 (cap.
10.000 m3 each) with fire satefy system and piping.
Erection of steel constructions and transfer pipelines with surface protection.
Mechanical works,
anticorrosive protection and insulation works.
TERM OF PROJECT EXECUTION:
10.2002-01.2004
TANKS Z-8,
Z-9,
Z-10
Supply and erection of the double-shell storage tanks no Z-8,
Z-9 & Z-10 (cap.
10.000 m3 each) with fire satefy system and piping.
Assembly of pipe-racks and transfer pipelines.
Erection of filling facilities,
pumps and equipment.
Mechanical works,
anticorrosive protection and insulation works in oil tanks terminal and railway terminal.
TERM OF PROJECT EXECUTION:
08.2000-08.2002
|