CLIENT:
DUO SA
SCOPE OF WORKS:
"Turn key" execution.
- 7 fixed-roof storage tanks capacity of 2000m3 each,
one tank capacity of 1000 m3
- tank shells were carried out with “rolled sheet” method,
- pump station for uploading and loading fuel,
- extention of the automatic pour stations,
- VRU unit,
- fire safety system: water tank,
pumps,
piping,
- sewage treatment plant with oil separator,
- compressor station,
- main switch chamber,
- underground sewage,
fire and potable water system,
- sewage system,
- electric wiring,
- erection period – 11 months,
- DUO fuel terminal was continuously operating during construction period.
TERM OF PROJECT EXECUTION:
1999 - 2000
|